2-22-09
 
 
 
We started by transferring a plumb line from the west wall (right) onto the top log on the south wall (left) and cutting off the excess. When we lift the next log, the pass end will fit tight against this cut which is the butt end of the south log. Since we plumbed the cut, our west log will already be plumb when we set it.
(click on the image to view movie)
 
Back on the ground, Matt trims off some remaining knots.
(click on the image to view movie)
     
 
Matt breaks out his big Stihl to make quick work of cutting the flare off the butt end.
(click on the image to view movie)
 
Matt works the Ford tractor to begin lifting the pass end first.
(click on the image to view movie)