Two pressure-treated 6x6 posts and a mounting panel made of pressure-treated 2x10s. This will hold our main disconnect and meter. |
|
The trench dug yesterday from the meter post to the house. We've connected and glued more conduit for the electric cable that will provide service to the house. |
John starts the last trench from the meter post to the transformer vault while Paul spots him. |
|
John cleans up the edges near the transformer. |
Now that this trench is finished, it's time to lay the last few pieces of conduit for the last section of electric cable. |
|
Paul applies PVC cement to the end of one of the joints. |
John fits the joints together while Paul taps the joint into place. |
|
Driving one of the two grounding rods needed for the meter post. |
Cutting the excess electric cable at the transformer vault. |
|
Finished! We now have our electric line run from the transformer to the meter, and from the meter to the house. |